Development Playbook
📘
How to Use This Playbook
Your single source of truth for the Subtext development process

This playbook is the authoritative guide for Subtext's acquisitions and development teams. It documents our standard processes, defines roles and responsibilities, and consolidates links to every template, workbook, and resource the team uses.

Use the left sidebar or the phase buttons below to navigate. Each section can be expanded to reveal detailed process guidance, step-by-step instructions, role assignments, risk callouts, and direct links to working templates. Placeholder links (shown in gray with dashed borders) will be updated as resources are uploaded and organized.

ℹ️
Keeping This Playbook CurrentProcesses and templates evolve. If you identify a gap or discrepancy between this guide and current practice, flag it to the EVP of Development so the playbook can be updated.
Phase 1

Land Acquisitions

From initial market screening through site identification, underwriting, and offer submission — the full acquisitions lifecycle at Subtext.

1
Market Selection
Four-step process from market ranking to Investment Committee approval

Subtext focuses its pursuit on Power 4 markets with solid fundamentals, including positive enrollment growth, supply and demand imbalance, limited pipeline, positive rent growth, and strong market occupancy. The market selection process is a disciplined, four-step funnel designed to allocate team resources only to markets with the highest probability of delivering an investable opportunity.

Step 1 Ranking Model

The Market Ranking Model is Subtext's quantitative framework for evaluating and prioritizing target markets across the country. It regresses a combination of current and lagged variables — capturing both the strength of the university and the strength of the student housing market — against rent growth, the variable most predictive of development performance. The output is a ranked list of markets used as the starting point for determining which warrant deeper analysis.

Methodology

The model uses a fixed effects panel regression, which analyzes longitudinal data by observing change within each school over time rather than comparing schools against one another. This isolates market-specific changes affecting rent growth and avoids false signals from unrelated movements at other schools. A Hausman Specification Test confirmed fixed effects over the random effects alternative. The complete dataset currently runs through the 2024–25 school year; fundamentals data runs further out, but RealPage occupancy has become unreliable and is being augmented or replaced by College House data where applicable.

Key Variables (2024 Backtest)

The 2024 backtest identified seven statistically significant variables. The most meaningful change from the 2023 backtest was the loss of Distance Learners — a reasonable development, as learning has returned largely in-person and on-campus headcount now hews closer to each market's student bed capacity.

  • December Prelease — Prelease level in the latest December (RealPage).
  • PBSH Occupancy — Privately-built student housing occupancy in the most recent month, non-inclusive of student-competitive (College House). Regression was originally run against RealPage data, but College House is now preferred given RealPage occupancy reliability issues.
  • 3-Year Change in Student Bed to Enrollment Ratio — (Private beds + university housing) ÷ full-time enrollment in 2028 minus the same ratio in 2025 (RealPage enrollment forecast; College House for pipeline).
  • April Prelease Change — YoY change in prelease level in the latest April data (RealPage).
  • Three-Year Change in Applications — Growth in applications over the last 3 years (IPEDS); additional IPEDS inputs are used to forecast expected application growth in 2028.
  • POSH Occupancy Last Year — December occupancy in all private student housing, including student-competitive (RealPage). Still reliable for 2024 data but being phased out next year regardless of statistical significance.
  • Growth in Out-of-State Undergrads — Three-year change in out-of-state freshmen at the university (IPEDS).
ℹ️
Forecasting caveatFive of the seven variables cannot be forecasted reliably — their inputs would themselves need to be forecasted, and the underlying relationships are tenuous. The three-year application growth forecast is acceptable (no secondary forecast required). The student bed to enrollment ratio is forecastable with reasonable confidence given pipeline data quality, though it relies on RealPage's enrollment forecast; a realistic in-house enrollment forecast would require a larger, more demographics-focused effort. College House's pipeline-dropout data is used to estimate completion rates for the "planned" pipeline: 50% for projects under 400 beds and 55% for projects over 400 beds.
Institutional Filter

In parallel with the rent-growth regression, a standard linear regression (with a year dummy) is run against new construction to identify which variables drive where peers and competitors deploy capital. The year dummy is used — rather than a fixed effects specification — to avoid picking up variables that simply happen to be high when construction is high, and to measure schools against each other more fairly. Four variables are significant: full-time enrollment less distance learners (virtually any enrollment variable can be swapped in), prior-year uncaptured demand within one mile of campus (excluding student-competitive), the 25th percentile ACT score of incoming freshmen, and the YoY change in asking rent three years prior. Construction is assigned to the year two years before completion (not the completion year) so the data does not lag as much. The same regression run against overall investment — including transactions — produced only size-related signals (enrollment and bed count), and the relationship between the two was not statistically significant.

How We Use the Model
  • The ranking model is continuously referenced and updated as market data evolves. It serves as a guide — not a rigid gating mechanism — for which markets should be analyzed.
  • Based on the ranking model and other qualitative factors, acquisition team leadership determines which markets are assigned to acquisition analysts for analysis.
  • The market analysis schedule, maintained in the Acquisitions Teams Channel, tracks all assignments, due dates, and next steps for each market under review.
Step 2 Phase 1 Analysis — Initial Market Screen

The Phase 1 Analysis is a high-level screening designed to confirm that a market meets Subtext's baseline investment criteria before committing significant analytical resources. The market must satisfy at least five of the eight requirements below to advance to Phase 2.

Subtext Market Requirements
Comp set rents greater than $900/bed
Full-time enrollment greater than 15,000 students
Market occupancy greater than 90%
Positive full-time enrollment growth for the past three years
Year-over-year rent growth greater than 3% for the past three years
Comp set preleasing lagging no more than 10% from prior year
Off-campus pipeline not greater than 10% of existing student housing supply
Capture rate not greater than 15% of current uncaptured demand

Upon completing the Phase 1 Analysis, the analyst circulates an email to the acquisitions team presenting the results using the template below. In addition to the eight qualifiers, the analyst should perform cursory research on the university and market to identify any other considerations — such as university growth plans, zoning changes, new pipeline projects, or upcoming stakeholder elections — that should be factored in. The Market Analysis FAQs provide additional guidance on supplemental research to include.

ℹ️
If the market is approved by acquisition team leadership, the analyst proceeds to the Phase 2 Analysis. Markets that do not meet the threshold should be documented in TermSheet (TS) with a brief explanation of the shortcomings.
Step 3 Phase 2 Analysis — Deep Dive

The Phase 2 Analysis is a comprehensive market study that typically takes approximately two weeks to prepare. By the time of the final presentation, the analyst should be an expert on the market and able to field any question raised by leadership or the Investment Committee.

1
Run the Market Analysis Workbook
Begin by running the market analysis workbook, which generates a standardized set of charts and tables covering enrollment trends, supply/demand dynamics, rent growth, pipeline, and affluence. Once pulled, analyze and synthesize the data into a coherent market narrative.
2
Complete the Full Market Analysis
This includes zoning research; conversations with university contacts about enrollment targets and campus growth plans; outreach to comp properties about prelease pace and rent levels; discussions with the City, land use attorney, or civil engineer about the political climate, potential zoning changes, and entitlement risks; and research into available incentives.
3
Reference the Market Analysis FAQs
Throughout the process, continuously cross-reference the Market Analysis FAQs to ensure no gaps in the analysis remain. This document captures common questions and edge cases that have come up in prior market reviews.
4
Internal Review with Team Lead
Prior to circulating the presentation to the broader team, the analyst must meet with the team lead to review the draft and address any gaps or open questions.
5
Circulate & Present
The presentation is circulated to the acquisition team no later than one business day prior to the group meeting. During the meeting, the analyst takes detailed notes on follow-up questions and additional research items.
6
Revised Presentation & TS Upload
Within one week of the initial presentation, the analyst circulates a revised version addressing all open questions. The final presentation is then uploaded to TermSheet with a summary of whether the market was approved. If not approved, the summary should include a clear explanation of the market's shortcomings.
Step 4 Investment Committee Approval

Markets that pass the Phase 2 Analysis are presented to the Investment Committee (IC) for final approval to begin active pursuit. The IC presentation is a polished, executive-level version of the Phase 2 work product, and should be prepared and reviewed following the same discipline as the Phase 2 process.

  • The Director of Acquisitions and analyst prepare the IC presentation using the approved template.
  • The EVP reviews the presentation prior to submission to the IC.
  • IC approval is required before any market tour is scheduled or site pursuit begins.
2
Market Pursuit
Coordinating the market tour and establishing on-the-ground intelligence

Upon IC approval to pursue a market, the acquisitions team moves quickly to establish on-the-ground intelligence, identify target sites, and build broker and city relationships. The market tour is the primary vehicle for this effort and must be executed with intention and preparation.

Market Tour Preparation
  • Within three weeks of IC approval, the Director of Acquisitions and the analyst coordinate a market tour date.
  • At least one week prior to the tour, the Director and analyst compile the Market Tour Packet — a comprehensive briefing document covering target areas, candidate sites, broker contacts, city planning staff, key questions, and a preliminary underwrite.
  • Prior to departure, the Director and analyst schedule a pre-tour review meeting with the VP of Acquisitions and the EVP of Development to confirm target areas, potential sites, and tour objectives.
Market Tour Objectives
  • Identify and physically evaluate target areas and specific sites within the desired walking radius.
  • Meet with potential brokers who are active in the student housing or commercial land market.
  • Meet with the city planning department, civil engineer, and/or land use attorney to understand the entitlement environment and any active or pending zoning changes.
  • Tour campus to understand circulation patterns, student housing demand drivers, and proximity dynamics.
  • Tour comparable properties to evaluate rent levels, amenity programming, occupancy, and lease pace.
💡
Reference the Market Tour Questions document throughout the tour to ensure all critical data points are captured in real time. Don't rely on memory — fill it out on-site.
Post-Tour Debrief
  • After the tour, the Director and analyst schedule a debrief with the VP of Acquisitions and EVP of Development covering tour highlights, target areas, candidate sites, completed Market Tour Questions, and a test underwrite.
  • The Market Tour Packet and completed Market Tour Questions are uploaded to TermSheet to document the pursuit activity.
3
Site Selection
Identifying and prioritizing target sites using spatial analysis and market fundamentals

Once the market tour is complete, site selection begins in earnest. This process combines data-driven spatial analysis via LandVision with ground-level market knowledge gained during the tour.

LandVision Setup
  • The analyst configures LandVision with the applicable layers for the target market. Layers include a combination of manual entries (e.g., pinned parcels, walking radius overlays) and shapefile uploads (e.g., zoning districts, flood zones, future land use maps).
  • Reference the LandVision Layer Guide for the standard layer configuration for student housing markets.
Site Prioritization Criteria
  • Walking radius first. Begin with sites that fall within our target walking radius from campus. These provide the "fall out of bed" location that is central to the Subtext product thesis.
  • Common ownership in assemblages. Look for parcels with common ownership to reduce the number of counterparties in an assemblage. Fewer sellers means fewer negotiating paths, faster execution, and reduced risk of one party derailing the deal.
  • Zoning analysis. Review current zoning, the future land use plan, and recent zoning approvals in the market to identify locations where our product is permitted by right or achievable through a manageable entitlement process.
  • Product type viability. Determine what product type is financially viable in the market based on achievable rents, construction pricing, property taxes, and operating expenses. Use the following minimum site size thresholds as a guide: High-rise requires at least 0.5 acres, podium requires at least 1 acre, and wrap requires at least 2 acres.
⚠️
Internal Alignment Before Outreach After the analyst and Director have discussed and prioritized candidate sites, a meeting with the VP of Acquisitions and EVP of Development should be scheduled to review and finalize the target site list before any outreach to landowners begins.
Landowner Outreach

Once the target site list is finalized, the team initiates outreach to landowners following the Owner Discussion Script. This script provides a framework for the initial conversation and helps ensure consistency in how Subtext introduces itself and its interest in the site.

4
Site Underwriting
Financial modeling, schedule, and program development for target sites

Site underwriting happens in parallel with — and closely informs — the site selection and entitlement processes. Before a model or schedule is submitted for internal review, the analyst must have a clear understanding of the site's zoning, potential product program, and construction constraints.

Underwriting Process Overview
  • Zoning & Entitlements First. Before modeling begins in earnest, the analyst should understand what is achievable on the site from a zoning and entitlement standpoint. What is allowed by right? What requires a variance or rezoning? What are the development standards (height, setbacks, FAR, parking, etc.)?
  • Program Development. Based on site constraints and market demand, develop a preliminary unit mix and program that is financially viable. The Program Document captures the project's key parameters — unit count, unit mix, gross square footage, amenity program, and parking — and is the foundation on which the financial model is built.
  • Financial Model. Run the financial model using the approved Subtext underwriting template. Ensure the model reflects current construction cost assumptions, market rents from the Phase 2 analysis, and current financing assumptions. All models must be reviewed by the Director of Acquisitions before submission to leadership.
  • Schedule. Develop a preliminary development schedule that reflects realistic entitlement timelines, design milestones, permit timelines, construction duration, and lease-up. Reference the Schedule Best Practices document when building the project schedule.
  • Test-Fit. Use TestFit to validate that the program fits on the site and is architecturally achievable. TestFit should be used early and often as program parameters are refined. Reference the TestFit Training Videos for guidance.
ℹ️
Standard Underwriting Questions A list of standard underwriting questions is maintained to prompt analysts to address all key assumptions before the model is circulated. Review this list before each model submission.
5
Offers & Letters of Intent
LOI preparation, submission requirements, and negotiation guidance

Before any LOI is submitted, the acquisition must be internally reviewed and approved. The following process and submission requirements apply to all LOI activity.

LOI Submission Package

The following materials must be prepared and submitted for internal review before an LOI is drafted or submitted to a seller:

  • Updated financial model reflecting current program, rents, costs, and financing assumptions
  • Preliminary project schedule
  • Program document with proposed unit mix, square footage, and parking
  • Summary of entitlement strategy and key risks
  • Completed LOI drafting questions (see resource link below)
LOI Structure & Key Terms

Subtext LOIs for land acquisitions are structured to reflect the following standard terms and timelines. Specific terms will vary by deal, but the following represent our typical starting point:

  • Earnest Money Deposit (EMD): Negotiated based on seller expectations; initial deposit is typically hard at a later milestone or upon satisfaction of key contingencies.
  • Due Diligence Period: Typically 90–120 days, during which the deposit is refundable. Extension options are desirable.
  • Closing Timeline: Typically 30 days following due diligence expiration, subject to entitlement milestones where applicable.
  • Contingencies: Standard contingencies include entitlement, financing, and environmental clearance. The extent of hard money and when it goes non-refundable is a key negotiating point.
Negotiation & Risk Items

The following provisions are commonly negotiated in land acquisition LOIs and Purchase Agreements. The list below reflects areas where Subtext has flexibility and items we typically push back on:

  • Hard money timing: Push to delay hard money as long as possible, ideally until after receipt of entitlement approvals or a major milestone.
  • Termination rights: Preserve broad termination rights during due diligence and at entitlement milestones. Sellers will push for more limited termination triggers.
  • Closing extensions: Negotiate the right to extend closing at a reasonable cost if entitlements are delayed.
  • Seller representations: Negotiate for robust reps on environmental condition, lease status, litigation, and title.
  • Access rights: Ensure broad access rights for due diligence activities, including environmental testing, survey work, and soil borings.
⚠️
All LOIs require EVP approval before submission. Do not submit an LOI to a seller or broker without obtaining written (email) sign-off from the EVP of Development. Include the final model, schedule, and program document in your approval request.
Phase 2

Pre-Development

From LOI execution through design, permitting, and Investment Committee approval — the pre-development phase sets the foundation for a successful project.

6
Acquisitions to Development Transition
Handing off a project from the acquisitions team to the development team

A clean, thorough handoff from acquisitions to development is critical to ensuring nothing falls through the cracks during the transition. The following process governs how projects are formally transferred from the acquisitions team to the development team after LOI execution.

1
EVP Assigns Development Team EVP
Once all LOIs are executed, the EVP of Development assigns a Development Manager (DM) and Development Associate (DA) to the project.
2
Transition Meeting Scheduled Director
Within one week of the EVP assignment, the Director of Acquisitions schedules a two-hour transition meeting. Required attendees: Director, Analyst, DM, DA, VP of Acquisitions, and EVP of Development.
3
Pre-Meeting Materials Prepared Director Analyst
Prior to the meeting, the Director and Analyst prepare and circulate: (1) the completed Acquisitions to Development Transition Template, (2) a final proforma, (3) a project schedule, (4) a completed deposit tracking spreadsheet, and (5) a completed lease tracking template. These materials must be shared with the development team at least 24 hours before the meeting.
4
Transition Meeting
The two-hour meeting is structured to provide a comprehensive transfer of institutional knowledge. Topics include: all contract terms and contingency dates, seller background and relationship dynamics, zoning and entitlement status, underwriting assumptions, project schedule, existing leases, consultant relationships, market context and comp data, city stakeholders and political environment, and any outstanding risks or open items.
💡
The transition meeting is one of the most important meetings on any deal. The development team is inheriting months of acquisitions work — treat this as a comprehensive knowledge transfer, not a summary review. Two hours is the minimum, not the target.
7
Contracts
PSA execution, lease management, and seller correspondence
DM Purchase Agreement Execution
Responsible RoleDevelopment Manager
DescriptionFinalize and execute the Purchase and Sale Agreement (PSA) with negotiated terms and contingencies. The PSA is the legal foundation of the transaction and must accurately reflect all business terms agreed upon during the LOI process.
Key RisksFailure to execute on time may result in loss of the deal or unfavorable renegotiation. Missing or poorly drafted contingencies can expose the company to significant financial or legal risk.
  • Coordinate with legal counsel (Holland & Knight or Polsinelli, per EVP direction) to finalize PSA language.
  • Ensure all critical contingencies are included: due diligence period, financing, entitlements, and environmental clearance.
  • Confirm execution deadline and signatory authority before routing for signatures.
  • After execution, calendar all critical dates and send invites to all relevant team members.
DM Purchase Agreement Review
Responsible RoleDevelopment Manager
DescriptionThoroughly review the draft and final PSA to confirm alignment with business terms and risk mitigation goals.
Key RisksMissed provisions or misaligned terms can expose the company to financial or legal liabilities that are difficult to unwind post-execution.
  • Review the draft with the internal team and real estate counsel prior to signature.
  • Focus on: contingencies, default and remedy provisions, access rights, reps and warranties, and closing conditions.
  • Flag any non-standard language or unusual legal exposure and escalate to the EVP before proceeding.
DA Project Meetings & Coordination
Responsible RoleDevelopment Associate
DescriptionCoordinate internal and external meetings related to the project kickoff and transaction management.
  • Schedule and manage regular internal team meetings and third-party check-ins.
  • Maintain a central log of meeting notes and action items in TermSheet.
  • Confirm decision points and ownership for each deal execution step.
DM Seller Updates & Correspondence
Responsible RoleDevelopment Manager
DescriptionManage ongoing communication with the seller throughout the due diligence and pre-closing period.
  • Establish a regular cadence for updates and data sharing (e.g., title, surveys, lease materials).
  • Use written correspondence to confirm key agreements or deliverable commitments.
  • Escalate any issues, delays, or adversarial dynamics to the EVP or legal counsel promptly.
DM Lease Abstracts & Estoppels
Responsible RoleDevelopment Manager
DescriptionReview, abstract, and validate all existing leases on the property, and obtain tenant estoppel certificates to confirm lease terms.
Key RisksOverlooked tenant rights, extension options, or purchase rights can limit redevelopment or cause schedule delays. Inconsistent lease representations in estoppels may create legal exposure.
  • The DA and DM jointly review all existing leases and complete the Lease Tracking Sheet for each.
  • Pay close attention to lease expiration dates and how they align with the projected demolition and construction schedule.
  • For commercial leases, confirm any extension options, purchase rights, co-tenancy provisions, or other encumbrances that could delay site control or complicate redevelopment.
  • Coordinate with legal counsel to obtain signed estoppel certificates from each tenant.
  • Verify that estoppel representations are consistent with the lease abstracts. Escalate any discrepancies immediately.
8
Due Diligence
Title, survey, environmental, and third-party investigations

Due diligence is the period during which the development team investigates all material risks associated with the site. The goal is to fully understand the physical, legal, and environmental condition of the property before going hard on deposits and committing to close.

⚠️
Before Waiving Due Diligence A checklist of required sign-offs must be completed before the team recommends waiving the due diligence contingency. All open items must be resolved or risk-assessed and accepted in writing by the EVP before waiver.
DM Title Review
Responsible RoleDevelopment Manager
Key RisksHidden liens, easements, or title defects may affect site usability or legal control of the property.
  • Once the team is comfortable spending money on the deal, notify legal counsel to order title and begin their review.
  • The EVP will designate whether Holland & Knight or Polsinelli will handle the transaction.
  • Review the preliminary title report carefully for easements, covenants, restrictions, and liens that could affect the project.
  • Confirm in writing before waiving due diligence that any title exceptions affecting the proposed project can be cleared, subordinated, or otherwise resolved.
DM Survey (ALTA/NSPS)
Responsible RoleDevelopment Manager
Key RisksBoundary disputes or encroachments may require design modifications or legal resolution prior to closing.
  • The DM is responsible for engaging and managing the surveyor. When requesting a proposal, confirm the delivery timeline upfront.
  • The survey proposal should include an ALTA/NSPS Survey with Table A Items: 1–4, 5, 6a, 6b, 7a, 7c, 8–11, 13–14, 16, 17, 18–20.
  • Release the surveyor to proceed when site access is confirmed and the team is ready to spend.
  • When reviewing the survey, confirm that all easements, plats, and other title exceptions appear and are accurately depicted.
  • Prior to waiving due diligence, obtain written confirmation from legal counsel that any survey exceptions affecting the proposed building footprint can be resolved.
PM Environmental Phase I & Phase II
Responsible RolePreconstruction Manager
Key RisksDiscovery of recognized environmental conditions (RECs) may trigger a Phase II, require remediation, delay permitting, and substantially increase project costs.
  • Order the Phase I Environmental Site Assessment (ESA) through a certified environmental consultant.
  • Ensure the consultant has site access and access to relevant historical documents (prior use, underground storage tanks, etc.).
  • If RECs are identified in the Phase I report, be prepared to commission a Phase II investigation.
  • Phase II should include a budget and schedule for potential remediation, and results must be coordinated with legal counsel and the investment team before waiving due diligence.
9
Entitlements & Approvals
Navigating the regulatory and political approval process

Entitlements are frequently the most time-consuming and unpredictable aspect of the pre-development process. Our approach prioritizes early stakeholder engagement, design efficiency, and proactive relationship building to maximize the probability of approval and minimize timeline risk.

Know the Process Before You Start
  • Before beginning any entitlement process, the development team must have a clear, documented understanding of every required approval — rezoning, variance, site plan, design review, conditional use permit, etc. — and the timeline associated with each.
  • Understand submittal requirements for every application before beginning design. If the city cannot provide a checklist, review prior approved submittals and clarify with city staff. The goal is to advance design only as far as required for each submittal — avoid showing unnecessary details that could restrict future flexibility.
  • Where renderings or visualizations are required for stakeholder presentations, clearly communicate that early materials represent conceptual designs subject to change.
Understanding City Priorities
  • Invest time early in understanding what city stakeholders, planning staff, and neighborhood associations care about most. This intelligence should directly inform design decisions and talking points.
  • Subtext's typical focus areas in entitlement discussions: streetscape quality, pedestrian experience, activation of ground-floor uses, community benefit provisions, and how the project relates to the surrounding neighborhood context.
  • Frame the project as a community asset — create a safe, vibrant, active pedestrian environment that benefits both residents and the surrounding community.
Proactive Stakeholder Engagement
  • Do not wait for the formal application process to begin outreach. The development team should proactively meet with city staff, neighborhood associations, adjacent property owners, and other key stakeholders before submitting any application.
  • The goal is to make stakeholders feel like partners in the process — give them a genuine opportunity to provide input before the plan is finalized.
  • A project website should be live before any public stakeholder meeting. This serves as the primary reference point for community members and media.
💡
Key Questions for Every Submittal: What must be shown at this stage? What will we be held to permanently? What can be refined later in the process? For example, confirm whether mechanical elements like louvers need to appear on early submittals or can be addressed in subsequent design review phases.
10
Underwriting
Ongoing financial model maintenance through pre-development

Underwriting doesn't end at LOI — the financial model must be continuously updated throughout pre-development to reflect new information as it is gathered. The goal is to ensure the investment thesis remains intact as design, entitlements, and market conditions evolve.

Core Underwriting Components
  • Unit Mix. The unit mix should be refined as the design progresses and as market data is updated. Changes to the unit mix have a direct impact on revenue projections and must be reflected in the model promptly.
  • Supply and Demand Report. Maintain a current view of market supply and demand dynamics. The supply and demand report should be refreshed whenever a new project is announced, a comp delivers, or rent data is updated. This report underpins the absorption and rent growth assumptions in the model.
  • Comp Property Report. Maintain an active comp set and update the comp property report to reflect current rent levels, occupancy, prelease pace, and amenity offerings. This report is the primary basis for the rent assumptions in the proforma.
  • Operating Expenses. Operating expense assumptions should be benchmarked against comparable Subtext assets and current management fee expectations. Update expenses as construction costs, tax estimates, and management structure are refined through pre-development.
ℹ️
The DM is responsible for ensuring the model is current before every IC presentation, Co-GP approval, and capital event. The EVP should never receive a model that does not reflect the latest project assumptions.
11
Design & Preconstruction
Program, design process, consultant selection, and construction preparation
Project Program
  • Focus Groups and Surveys. Where possible, conduct resident focus groups and market surveys to validate unit mix assumptions, amenity preferences, and program decisions. Reference the standard survey questions template and review prior survey results from comparable Subtext markets before designing new research instruments.
  • Survey results should inform — but not drive — program decisions. The development team is responsible for synthesizing resident input with financial constraints and market data.
Architect Selection & Design Proposals
  • Design proposals should be solicited using a structured RFP process. The RFP should clearly define scope, schedule expectations, deliverables by phase, and fee structure.
  • At-Risk Structure. Where possible, Subtext structures design contracts to bring major consultants (structural, MEP, civil) under the architect of record. This simplifies contract management, establishes clear liability, and reduces coordination gaps between disciplines.
  • Reference the Design Proposal Best Practices document for guidance on evaluating proposals, negotiating fees, and structuring consultant agreements.
Design Process & Reviews
  • The internal concept design process is governed by the Design Flow Chart, which defines deliverables, review milestones, and decision gates from schematic design through construction documents.
  • Best practices for design set reviews: review sets systematically using the Design Deliverable Checklist; document all comments in writing; confirm responses from the design team in writing before proceeding to the next phase.
  • Standard unit plans should be the starting point for all new projects. Deviations from standard plans require written justification and EVP approval.
  • The Design Handbook and Outline Spec define Subtext's minimum product standards and should be incorporated into every project scope of work.
  • Design metrics (cost per square foot, efficiency ratios, unit mix composition) should be tracked and benchmarked against prior projects throughout the design process.
Value Engineering

VE should be approached proactively — not reactively. The standard VE items list captures categories where cost savings have been achieved on prior projects without compromising product quality or resident experience. The DM should reference this list when reviewing preliminary pricing and push for VE analysis before GMP is established.

12
Permits
Building permit strategy and timeline management

The building permit process is a critical-path item that must be tracked with the same rigor as entitlements and design. Permitting timelines vary significantly by jurisdiction and can meaningfully impact the project schedule and cost if not planned for properly.

  • Engage the city's building department early — ideally during entitlements — to understand the permitting process, required submissions, and review timelines for projects of this scale and type.
  • Where available, pursue phased or foundation permits to allow early construction activities to begin while the full permit is under review.
  • Identify the city's preferred plan review track (standard, expedited, third-party review) and build the appropriate timeline and cost into the project schedule and budget.
  • The DM is responsible for maintaining a permit log that tracks all submitted, pending, approved, and expired permits on the project.
  • Coordinate with the Preconstruction Manager to ensure all plan check comments are responded to promptly and that resubmittal timelines are tracked in the project schedule.
13
Investment Committee
Preparing and presenting for IC approval milestones

Projects require Investment Committee approval at multiple milestones throughout the development lifecycle, including initial market approval, project greenlight, capital events, and budget changes. The following guidance applies to all IC presentations.

  • IC presentations should be concise, visually clear, and data-driven. The IC relies on the development team's analysis and judgment — present findings with confidence and a clear recommendation.
  • All financial models presented to the IC must be reviewed and approved by the EVP before submission. No model goes to IC without EVP sign-off.
  • Anticipate questions: prepare a diligence backup package covering key assumptions, market data, and sensitivities. Know the answers before the meeting.
  • Meeting notes and the IC decision should be captured in TermSheet within 24 hours of the meeting.
14
Co-GP Approvals
Managing approval requirements with joint venture partners

Where Subtext has Co-GP partners on a project, the development team must understand and adhere to the approval rights and notification requirements set forth in the joint venture agreement. Failure to obtain required Co-GP approvals before acting can constitute a default under the JV agreement.

  • At project kickoff, the DM should review the JV agreement with legal counsel and document all decisions that require Co-GP approval, consent, or notification.
  • Maintain a Co-GP approval log and build approval timelines into the project schedule — Co-GP review periods can impact critical path milestones.
  • Prepare Co-GP approval packages with the same rigor as IC presentations. Co-GP partners are sophisticated — provide complete, well-organized materials with adequate review time.
  • All Co-GP communications on material items should be in writing and copied to the EVP.
Phase 3

Capital

Term sheet negotiation, lender and equity partner management, and capital event execution.

15
Capital & Term Sheet
Negotiating debt and equity terms and managing capital events

The capital process encompasses the sourcing, negotiation, and closing of construction debt and equity for each project. The development team works closely with Subtext's capital markets relationships and external advisors to structure the optimal capital stack for each transaction.

Term Sheet — Key Risks & Negotiation Points
  • Recourse and Carve-outs. Construction loans are typically non-recourse with standard carve-outs. Push to limit the scope and definition of bad boy carve-outs and ensure they are symmetrical where possible.
  • Interest Reserve. Ensure the interest reserve is sized appropriately for the full construction duration plus a contingency buffer. Under-reserved interest can create a liquidity crunch mid-construction.
  • Completion Guarantee. Understand the completion guarantee terms before term sheet execution. Scope and duration should be carefully reviewed by legal counsel.
  • Equity Funding Order. Confirm the equity funding waterfall and contribution timing with all equity partners before construction loan closing.
  • Extension Options. Negotiate extension options on construction loans to protect against entitlement or construction delays.
  • Lender Approval Rights. Review and limit lender approval rights over project decisions — overly broad approval rights can slow decision-making and create friction during construction.
Phase 4

Construction

Budget management, contractor oversight, and value engineering during the construction phase.

16
Construction Management
Budget tracking, draw management, and project oversight

During construction, the development team's primary responsibilities are budget management, schedule oversight, lender compliance, and contractor relationship management. The following guidance reflects Subtext's standard practices during the construction phase.

Budget Tracking
  • The DM maintains the project budget on a continuous basis throughout construction. Budget variance reports are prepared monthly and reviewed with the EVP.
  • All budget changes — regardless of size — must be documented via a formal change order or budget transfer process. Verbal approvals are not sufficient.
  • The DM is responsible for ensuring the construction loan draw schedule aligns with the project budget and lender requirements. Draw packages must be complete and accurate before submission to the lender.
  • Track contingency usage carefully. Alert the EVP when contingency falls below 50% of the original allocation so proactive steps can be taken.
Value Engineering During Construction
  • VE during construction should focus on scope changes that reduce cost without compromising the resident experience, design intent, or project schedule.
  • All material VE changes must be reviewed by the EVP and design team before execution. Changes that affect the exterior, unit finishes, or amenity programming require additional scrutiny.
  • Document all VE decisions in writing, including the rationale for acceptance or rejection, and maintain a running VE log throughout construction.
ℹ️
Additional Construction Guidance Detailed construction management protocols, GC oversight processes, and draw management procedures are being developed in coordination with the construction team. This section will be updated as those protocols are finalized.
Phase 5

Temporary Leasing Office

From LOI execution through TLO opening — the full kick-off and construction process for the temporary leasing office.

17
TLO Kick-Off Process
Sequence, responsibilities, and schedule from LOI to opening

The Temporary Leasing Office (TLO) is a critical pre-opening asset that enables the leasing team to begin pre-leasing before the project delivers. The following process governs the TLO kick-off from initial planning through opening.

1
LOI Executed
TLO planning begins upon execution of the LOI for the TLO space.
2
Floor Plan Distribution DM
The DM sends the DR floor plan to the DM, Interior Designer (ID), and Construction Manager (CM).
3
Project Schedule Drafted DM
The DM prepares a preliminary project schedule using the TLO Schedule Template.
4
ESG Proposal DM
The DM sends the floor plan and schedule to ESG (Melissa and Maggie) to obtain a proposal, copying the ID, CM, and DR.
5
Internal Kick-Off Call DM
The DM organizes an internal kick-off call with the ID, CM, DR, and Operations team to align on scope, schedule, and responsibilities.
6
TermSheet Tasks Created DM
The DM sets up TS tasks aligned with the project schedule milestones.
7
GC Engagement & Selection CM
The CM engages GC candidates, discusses the schedule, and manages the GC selection process.
Standard TLO Schedule
🎨 Design — 4 weeks
💲 Pricing — 2 weeks
✂️ VE Process — 2 weeks
🎨 Final Design — 2 weeks
📜 Submit for Permit — 1 week
💲 Final Pricing — 2 weeks
🔨 Construction — 12 weeks
✅ Punch — 2 weeks
🛋️ Furniture Install — 1 week
🪴 Staging/Accessories — 1 week
Phase 6

Delivery

Project closeout, punch list management, and transition to operations.

18
Delivery & Redzone
Final project delivery, punchlist, and operations handoff

The Redzone period covers the final weeks before a project's opening and the initial weeks of operations, when all construction, leasing, marketing, and operational activities converge. This is one of the highest-risk periods in the project lifecycle and requires proactive coordination across every team.

Redzone Coordination
  • The DM is responsible for leading weekly Redzone meetings with representatives from construction, leasing, operations, marketing, and management during the final 90 days before opening.
  • All open punch list items must be tracked in a shared punch list log, with owner assignments and target completion dates. The DM reviews the punch list with the GC weekly and escalates items at risk of missing the opening date.
  • Certificate of Occupancy (CO) timing must be tracked closely and communicated to the leasing team, as it drives the move-in schedule.
  • The development team coordinates the formal operations handoff, including the transfer of warranties, equipment manuals, as-built drawings, and all construction documentation to the property management team.
Post-Delivery Closeout
  • Following stabilization, the DM prepares a project closeout report documenting final budget outcomes, schedule performance, key lessons learned, and recommendations for future projects.
  • All project files, contracts, permits, and as-built drawings are archived in TermSheet upon project closeout.
ℹ️
Redzone Playbook Detailed Redzone protocols, meeting templates, and punch list management procedures are maintained in the Redzone section of TermSheet. Reference those resources throughout the delivery period.
Subtext Development Playbook
Last updated: March 2026 · EVP of Development
For updates or corrections, contact the Development team.